News July 2017 - July 2019

July 2017 - July 2019

July 2017 - July 2019
In July 2017 HoHo Next is located on the third floor (the two basements of HoHo Tower and Next are finished), during the construction meetings they will discuss polishing and execution plans, door lists, building services, the color of the windows, approvals of the MA19 regarding sound insulation, the detailed planning of the portals - just to name a few. This all in preparation for the September, from there began the installation of wood elements. Only two years later, in July 2019, only interior work takes place for the tenant development. The façade is finished and the scaffolding is being gradually removed so that the HoHo Vienna can be considered in its final state shortly!